123N PDFTitle:Building (Minor Works) RegulationGazette Number:E.R. 2 of 2012
Section:35Heading:Documents to be submitted on completion of class II minor works that are demolition worksVersion Date:02/08/2012


Within 14 days after the date of completion of any class II minor works that are demolition works, the prescribed registered contractor appointed under section 28 in respect of the works must submit to the Building Authority¡X

    (a) if the works as completed are different from those shown in the prescribed plans and details referred to in section 33(c), the revised prescribed plans and details showing the works as completed;
    (b) photographs showing the works as completed; and
    (c) a certificate in the specified form, in which the contractor¡X
        (i) has certified that the works have been carried out in accordance with the Ordinance and the prescribed plans and details referred to in paragraph (a) or section 33(c);
        (ii) has confirmed the date on which the works were completed; and
        (iii) has certified that any land or street affected by the works has an adequate margin of safety and any structure remaining on the premises is structurally safe in the opinion of the contractor.