Chapter: | 215
![]() | Title: | EASTERN HARBOUR CROSSING ORDINANCE | Gazette Number: | |
| Section: | 22 | Heading: | Road Company to submit a construction programme | Version Date: | 30/06/1997 |
(1) As soon as practicable after the commencement of this Ordinance, the Road Company shall submit to the Director for his approval a programme for the carrying out of the construction works and the construction works shall be carried out in accordance with such programme as so approved.
(2) The Director may approve or disapprove the programme submitted under subsection (1) or approve it in part and disapprove it in part.
(3) The Road Company may at any time apply to the Director for a variation of the programme approved under subsection (2) and any variation approved by the Director under this subsection shall be deemed to form part of the programme approved under subsection (2).