Documents to be submitted before commencement of class II minor works
Version Date:
02/08/2012
Not less than 7 days before the commencement of any class II minor works, the prescribed registered contractor appointed under section 28 in respect of the works must submit to the Building Authority¡X
(a) a notification in the specified form, in which¡X
(i) the person who arranged for the works to be carried out has specified the contractor as the prescribed registered contractor appointed under section 28 in respect of the works;
(ii) the contractor has confirmed the appointment and the date on which the works are to be commenced;
(iii) if the works comprise repairs, alterations or additions to any building, the contractor has certified that, after inspecting the building, the contractor is of the opinion that the building is capable of bearing the loads and stresses which may be increased or altered in any way as a result of the works; and
(iv) if the works involve the erection of a signboard, the person for whom the signboard is to be erected has provided the particulars of the person as required by the Authority;
(b) photographs showing the physical condition of the premises where the works are to be carried out; and
(c) prescribed plans and details of the works.