The Company shall complete the construction works within-

        (a) 48 months beginning on the start of construction; or
        (b) such extended period as may be allowed by the Director-
          (i) on any ground specified for that purpose in the project agreement; and
          (ii) in accordance with that agreement.
(Enacted 1993)